Construction management and claims consulting

Subcontractor claims and defense, built from the project record.

The Siewell Group supports subcontractors on data center and industrial projects with claims preparation, defense against backcharges and notices to cure, schedule and delay analysis, and document control from project award.

Revised schedule, 1 notice

A milestone moved left 79 days. Pricing was due in 6.

Largest milestone pull-in79 days
Time given to price the impact6 days
The revised schedule arrived as a PDF with no native P6 file. The version comparison started the day the notice arrived, and the native file request went on the record before the pricing deadline.
  • Requests for equitable adjustment
  • Backcharge contests
  • Notice to cure response
  • Acceleration claims
  • Time impact analysis
  • Primavera P6
  • Deposition support
  • Timecard audits
  • Warranty claim defense
  • Subcontract redlines
  • Document control from award

Retained at award

Subcontractors retain The Siewell Group early in the project as the document control collection point. When a notice to cure, a change order dispute, or a cost, delay, or acceleration disagreement comes up, it is addressed against an organized project record, with gaps and notice requirements flagged early.

From the record

Situations from current client work

24Change orders sent back through review

An owner's representative reissued the submission instructions mid-stream and disregarded everything previously submitted. The documented return reasons concerned submission quality, not a determination of entitlement: unreadable pink slips, hours that differed between cover sheet and crew report, missing signatures and dates, cropped scans, and equipment ID numbers on the wrong request.

2 weeksTesting acceleration requested

A GC asked an electrical subcontractor to price pulling third-party acceptance testing forward 2 weeks. The testing was never in the subcontractor's scope. 2 replies were drafted for the subcontractor's letterhead: the testing is outside scope, and a signed change order comes before any acceleration cost.

1 line"Does this affect any scheduled milestones?"

2 weeks after a change proposal went in, the GC asked 1 question. The subcontract flowed down specifications requiring an updated schedule with every change quotation and a time impact analysis with every proposed modification. The sections went to the client's managers that evening, with citations.

Clients, owners, general contractors, projects, people, and dollar figures are not named.